Coordinated As-Built Revit Modeling: A Single-Level Restaurant, Chattanooga

A dedicated team of four architects delivered a coordinated, clash-free as-built Revit model for an 8,500 sq. ft. restaurant in 9 working days.

As-built Revit model of a single-level restaurant in Chattanooga
About

Project Overview

Short timelines put production pressure on small architecture firms based in Indianapolis and Chattanooga. They needed an as-built model of a single-level, 8,500 sq. ft. restaurant. They brought us in to add production capacity for this one-off project. Our scope covered as-built drafting in Revit at LOD 350 and a fully coordinated, clash-free model. A dedicated architecture team of four delivered it in 9 working days, and later the client confirmed the output matched their expectations.

Level of Development: LOD 350
Project Area: 8,500 Sq. Ft.
Location: Chattanooga, USA
Team size: 4
Exterior of the single-level restaurant modeled in Revit
Tools We Use

Inside the Tools You Already Use

Revit lets our team build, check, and coordinate the as-built model for the restaurant in one shared environment.

RevitRevit
Project Deliverables

Input Vs Output

Client's architecture team handed over their project inputs, and our team returned a finished, coordinated model within nine working days.

What We Received

  • As-built information
  • Project requirements and LOD 350 specification
  • Milestone and deadline expectations

What We Delivered

  • As-built Revit model
  • Clash report and BIM coordination
  • Milestone-based progress updates
Get A Free Quote
Challenges

Pain Points of The Client

A small architecture team with a nine-day deadline struggled to keep production, quality, and coordination on track for one restaurant.

01

Limited Team Capacity

A small team of architects had little room to take on as-built modeling.

02

Tight Delivery Window

The project had a 9-working-day window, so slow handoffs were not an option.

03

Quality and Rework Worries

The client worried about quality and rework, and the schedule had no room for either.

04

Coordination With Project Management

The model had to be fully coordinated and clash-free, with project management involved throughout.

Our Approach

How We Solved Them

Each challenge got a direct answer, built around a dedicated team, daily checks, and steady communication with the client.

Dedicated Team of Four

Four resources worked only on this project, so the client dealt with one consistent team throughout.

Daily Milestones and Quality Checks

Our project manager tracked daily milestones and checked quality each day to hold the deadline.

Internal Quality Checks Before Submission

Our team ran internal quality checks before submission, and errors and revision cycles dropped 40%.

Clear Communication and Escalation

We kept 4 hours of overlap, sent milestone updates, and used Root Cause Analysis for escalations.

Execution Strategy

End-to-End Project Delivery Through a Phase-Controlled Approach

Our team worked through six stages, from scope alignment to final delivery, so the project stayed on track and deadlines were achieved.

  1. Alignment with Scope and Standard

    We confirmed the as-built scope, LOD 350 requirement and deliverables with the client before any modeling began.

    01
    01

    Alignment with Scope and Standard

    We confirmed the as-built scope, LOD 350 requirement and deliverables with the client before any modeling began.

  2. 02

    Team Setup

    Three dedicated resources joined the project and our project manager planned daily milestones for the project schedule.

    02

    Team Setup

    Three dedicated resources joined the project and our project manager planned daily milestones for the project schedule.

  3. As-built Modeling

    VBS team prepared the model of single-level restaurant in Revit. Whereas project manager tracked daily milestone progress.

    03
    03

    As-built Modeling

    VBS team prepared the model of single-level restaurant in Revit. Whereas project manager tracked daily milestone progress.

  4. 04

    Daily checks and coordination

    Our project manager was involved in coordination. Reviewed the model every day. This helped us identify and resolve clashes early before submission.

    04

    Daily checks and coordination

    Our project manager was involved in coordination. Reviewed the model every day. This helped us identify and resolve clashes early before submission.

  5. Internal Review and Delivery

    We did an internal review of quality before submission and submitted the coordinated model on time.

    05
    05

    Internal Review and Delivery

    We did an internal review of quality before submission and submitted the coordinated model on time.

  6. 06

    Final Model Handover

    Delivered a fully coordinated clash free as-built model. The client reviewed the delivered files and shared that the output matched their expectations for the project.

    06

    Final Model Handover

    Delivered a fully coordinated clash free as-built model. The client reviewed the delivered files and shared that the output matched their expectations for the project.

Project Outcomes

Coordinated. Approved. Delivered.

This engagement delivered coordinated as-built models and consistent project support to the client and 8 hours of capacity back daily.

Clash-Free As-Built Model

Our team delivered a fully coordinated as-built model of the 8,500 sq. ft. single-level restaurant.

Freed Daily Capacity of Client Team

Our team freed up 8 hours of the client's in-house capacity every day.

Internally Checked Files

Every file went through our internal quality check before it was submitted to the client.

Milestone-Based Updates

We updated the client at each milestone and kept 4 hours of time-zone overlap.

Confirmed Client Satisfaction

The client was happy, with the quality of the results. They confirmed that the outputs met their expectations.